Spread setup over the batch
A setup is done once per batch, so one piece carries only a share of it. Set the batch size and watch the norm per piece change.
On the canvas
The operation "Lathe work"; its step "Set up the machine" already has the type "Setup". Under the operation is the card of its result. On the right the "Properties" panel is open; the card shows the same rows as the "Result" panel.
Steps
- Click the operation "Lathe work". On the card: P โ 11.38, ST โ 6.16, P1 โ 17.54. The batch is one piece, so it carries the whole setup.
- In "Properties", in the section "Parameters", type 10 into the field "Min Batch Size" and press Enter. The row P1 becomes 11.99.
- Type 100 into the same field and press Enter. The row P1 becomes 11.44.
Check
The rows P and ST did not change. The row P1 holds 11.44, and beside it 0.5% โ by that much the norm per piece is above P.
If it did not work
- The number was not applied โ you did not press Enter.
- "Properties" has no section "Parameters" โ a step is selected. The batch size belongs to the operation.
- The card is not seen โ a panel covers it or the view has moved. Press "Start over" above the example.
The rule
P1 is the norm per piece: P plus setup and preparation spread over the batch. The rows ST, PR and F1โP1 are in the result of an operation, a recipe and a product. A step and an action do not have them.