Reading Results
Every element on the canvas displays a Result block — a set of calculated metrics that update automatically when you change factors, structure, or parameters. This document explains what each metric means and how to interpret it.
Result block location
The Result block appears on the canvas element itself and in the Properties panel when an element is selected. You can expand or collapse it, toggle its visibility, and change the display unit.
Time components
Four primary time values are calculated at every level of the hierarchy. For the complete definitions of every metric, see Time Structure.
- F (Full Time) — total time: human + machine
- H (Human Time) — personnel working time at the workstation
- M (Machine Time) — equipment operating time, with or without human involvement
- P (Part Time) — time to produce one unit, the standard; accounts for parallel execution of human and machine work
After P, two percentages are shown — main transitions and auxiliary transitions.
Cycle and deviation
CT — Cycle Time
The expected production cycle duration, followed by the expected deviation.
L — Expected Deviation
A normalised characteristic of the expected deviation of operation execution time from the nominal value during repeated execution.
L is stored as a dimensionless value (mathematical expectation of relative deviation) but displayed in time units. It serves as the expected cycle deviation.
- L is not tolerance
- L is not worst case
- L is typical (expected) deviation
Quality metrics
Three quality metrics describe the statistical stability of operation timing. For the full calculation model, see Quality Metrics.
- Q (Quality Level) — sigma equivalent of timing stability, range 3.0–5.8. Higher Q = more predictable. Q does not evaluate product quality — it measures time predictability.
- D (DPMO) — expected time deviations per million executions. Derived from Q via the normal distribution. This is a time defect, not a product defect.
- S (Stability) — normalised 0–1 score. Low stability → wide time distribution → more deviations.
Overhead and adjusted values
ST — Setup Time
Full stop for reconfiguration and preparation for the next product release. Driven by technology and organisation of the production process, plus equipment maintenance time required specifically for this operation.
Reduces the available working time budget on first start or changeover from a different product type.
PR — Preparing Time
Time for one-time per-shift operation preparation, independent of the number of items — setup, adjustment, tool preparation.
Reduces the available working time budget every shift.
F1, H1, M1, P1 — Adjusted values
Per-piece times including the distribution of preparatory and setup overhead across the batch:
P1 = P + (PR + ST) / (batch size × capacity)
The percentage shown after each adjusted value indicates the contribution of preparation and setup to the total time.
Adjusted values answer: "What is the real cost per unit when overhead is included?" A small batch with large setup time will have P1 significantly higher than P.
Main and auxiliary breakdown
After P (Part Time), two percentages are displayed:
- First percentage — labour intensity determined by main transitions (direct processing)
- Second percentage — labour intensity determined by auxiliary transitions (supporting work)
This breakdown helps identify whether the cycle is dominated by productive work or by handling, clamping, measuring, and other auxiliary operations.
Rejection limits
At the operation level, the result includes rejection limits — the statistical boundaries beyond which a time observation is considered a deviation:
- rjl_min — lower rejection limit
- rjl_max — upper rejection limit
These are derived from the quality level (Q) and the physical min/max boundaries of the operation. Observations falling outside these limits are counted as DPMO events.
Display units
Each element's result can be displayed in one of four units:
- Raw — internal base units (1/1000 of a minute)
- Seconds — real-time seconds
- Hours — decimal hours
- Time format — HH:MM:SS
Switch units in the Properties panel. The choice is per-element and does not affect calculations.
Expanding and collapsing
The Result block has two states:
- Collapsed — shows only the primary time components (F, H, M, P)
- Expanded — shows all metrics including CT, Q, D, S, L, ST, PR, adjusted values, and breakdown percentages
Toggle the expanded state by clicking the Result block header on the canvas or through the Properties panel.