Order the assembly operations
A board is first printed with paste, then the components are placed, then it is reflowed. The order of operations in a recipe is changed on the bus — put the placement before the reflow.
On the canvas
The Recipe (the technological process) "Assembly" with three operations in the wrong order: "Paste printing", "Reflow", "Placement". The panels are closed; their buttons are at the top of the canvas.
Steps
- Right-click the recipe "Assembly" and choose "Children on a bus". The operations line up on a vertical line — the bus.
- Drag the operation "Placement" up, above the operation "Reflow", and release. The operations swap places.
- Right-click "Assembly" again and choose "Children on a bus". The bus is gone, the new order stays.
Check
The operations stand like this: "Paste printing", "Placement", "Reflow".
If it did not work
- The operation moved together with its neighbours and the order did not change — the bus is not on. Without the bus the children move only as a whole.
- The operation went back — you released it before it got above the neighbour. Drag along the bus until the neighbour gives way.
- The button "Start over" above the example returns the scene to its start.
The rule
On the bus the order of an operation is its height: the higher, the earlier. The time of the recipe does not depend on the order, but the route and the card follow it.