Step Types & Time Groups
Every Step in a process has a type that determines which time group its duration falls into. This classification controls how the step's time is aggregated at the operation and product levels โ whether it forms the production cycle, reduces the available shift fund, or is accounted as setup overhead.
Three Time Groups
Time groups define how a step's duration is used in planning:
Main โ Cycle Time
Steps in this group form the production cycle โ the repeating work performed for every unit. Their durations aggregate into the Part time (P) of the operation.
- Directly determines takt time and throughput
- Includes both value-adding work and the auxiliary actions that enable it
Preparing โ Shift Fund Deduction
Steps in this group represent recurring overhead that reduces the available working time each shift. Their durations aggregate into the Preparing time (PR) at the operation level.
- Performed once per shift regardless of batch size
- Distributed across all units produced during the shift
- Examples: receiving instructions, workplace cleaning, tool preparation, regulated breaks
Setup & Other โ First-Start Deduction
Steps in this group represent overhead incurred at first start or changeover. Their durations aggregate into the Setup time (ST) at the operation level.
- Incurred once per batch or when switching between product types
- Distributed across all units in the batch
- Examples: equipment reconfiguration, adjustment runs, process verification
Nine Step Types
Each step type belongs to exactly one time group. The group is assigned automatically when you select a type โ it cannot be edited independently.
Main Group
- Main โ The core productive work. Direct machining, assembly, forming, chemical treatment, or other primary technological actions that transform the workpiece
- Auxiliary โ Actions directly necessary to enable the main work. Loading/unloading, clamping, positioning, measuring during the cycle, changing tools between passes
Preparing Group
- Organizational โ Receiving tasks, reporting, transferring information to accounting and operational systems, coordinating with other workstations
- Workplace Maintenance โ Service specific to the technological operation: cleaning the work area, disposing of waste, checking safety systems, replenishing consumables
- Preparing โ Setup and teardown actions performed once per shift. Reading drawings, installing fixtures, adjusting machine parameters at shift start, returning tools at shift end
- Rest & Personal Needs โ Separately allocated time for personnel hygiene at production facilities related to contamination, specific conditions, or long work cycles
Setup & Other Group
- Setup โ Full stop for readjustment and preparation for release of another product. Changing dies, reprogramming CNC, replacing fixtures, test runs for a new product
- Technological Needs โ Time-outs due to technology and organization of the production process. Cooling intervals, curing periods, mandatory waiting between operations
- Equipment Maintenance โ Time spent on maintaining equipment required specifically for this operation. Lubrication, calibration, minor adjustments that are not part of shift-level maintenance
Setting the Step Type
The step type is set in the properties panel when a Step element is selected. A dropdown lists all nine types, visually separated into three groups by dividers. Selecting a type:
- Automatically assigns the correct time group
- Updates the group badge displayed next to the dropdown
- Updates the visual indicator on the step element on the canvas
The group badge shows the localized group name and a visual icon corresponding to the current group.
The type change goes through the command system and is fully undoable.
How Types Affect the Result
At the operation level, steps are aggregated by group:
- Main group steps form the cycle โ their times produce F, H, M, P
- Preparing group steps produce the PR (Preparing) value
- Setup & Other group steps produce the ST (Setup) value
The adjusted per-unit values (F1, H1, M1, P1) then incorporate PR and ST distributed across the batch:
P1 = P + (PR + ST) / (batch size ร capacity)
This means changing a step's type from Main to Preparing moves its time out of the cycle and into the shift fund deduction โ the operation's P decreases but PR increases.
Choosing the correct step type is critical for accurate time standards. If auxiliary work (clamping, measuring) is classified as Main instead of Auxiliary, the main/auxiliary breakdown percentages will be misleading. If shift-level activities are placed in the Setup group instead of Preparing, the batch-size sensitivity of the result changes.
Intensity โ Main Group Only
The Intensity property is available only for steps in the Main group. It describes the physical effort level of the work and influences quality metrics.
Steps in the Preparing and Setup & Other groups do not display the intensity block in the properties panel.
Practical Guide for Type Selection
When deciding which type to assign to a step:
- Is the work repeated for every unit? โ Main group (Main or Auxiliary)
- Does the work produce or directly transform the product? โ Main
- Does the work enable or support the main action within the cycle? โ Auxiliary
- Is it done once per shift, regardless of output? โ Preparing group
- Is it done once per batch or at changeover? โ Setup & Other group
- Is it a scheduled break or hygiene requirement? โ Rest & Personal Needs
- Is it mandated by the process technology itself (cooling, curing)? โ Technological Needs
- Is it specific to the equipment used in this operation? โ Equipment Maintenance (if per-batch) or Workplace Maintenance (if per-shift)