Time Breakdown
Every element on the canvas has a calculated time result. This document explains how time flows through the hierarchy and how the final per-piece time is assembled.
The Calculation Pipeline
Time is computed bottom-up through four levels:
- Microelement โ base time from the BES table, adjusted by quality factors, numerical factors, and a multiplier. Machine-type microelements split the result into human and machine portions based on the mechanisation level.
- Step โ sums all child actions and microelements, applies intensity factors, builds a breakdown by tag values, and computes weighted mechanisation and production-type averages.
- Operation โ groups steps by type, separates cycle time from overhead, divides by batch size and capacity, and produces the per-piece time.
- Product โ sums all child operations and processes with intensity scaling.
Time Components
Every result has four base components:
- F (full) โ total time, human + machine
- H (human) โ time the operator works
- M (machine) โ time the equipment runs autonomously
- P (part) โ cycle time per piece: the greater of human and machine, adjusted by employment
At the operation level and above, additional components appear:
- Setup โ time for one-off batch preparation (e.g. tool changes, calibration)
- Prep โ time repeated each shift (e.g. receiving tasks, workplace cleanup)
- P1 โ the final per-piece time: cycle time + overhead amortised across the batch
Step Types and Time Groups
The 9 step types are grouped into three categories. For the complete reference, see Step Types & Time Groups.
- Main group (Main, Auxiliary) โ forms the cycle time
- Preparing group (Organisational, Workplace maintenance, Preparing, Rest & personal needs) โ per-shift overhead, divided by batch size per shift
- Setup group (Setup, Technological needs, Equipment maintenance) โ per-batch overhead, divided by total batch size
The Per-Piece Formula
At the operation level:
- part = main_cycle_sum ร multiplier / capacity
- overhead per piece = (setup + prep) / batch / capacity
- P1 = part + overhead per piece
This is the key formula. Increasing the batch size reduces the per-piece overhead. Increasing capacity (parallel processing) reduces both the cycle portion and the overhead portion.
Tag-Based Breakdown
Each action can carry tags in three dimensions: target, carrier, and stream. The calculation records how much of the part time comes from each tag value.
partBreakdown
A map from tag values to their time contributions within the cycle only. The sum of all values in each dimension equals the `part` time. Untagged actions use a special key (โ1).
p1Breakdown
The same breakdown but for the per-piece time โ it includes the overhead portion distributed proportionally across tag values. The sum of all values equals `P1`.
These breakdowns power the visual bar charts in the passport panel, showing what percentage of time goes to production vs. waste, physical vs. digital work, or value-adding vs. support activities.
Quality Statistics
Alongside time, the calculator produces quality metrics at every level: QL, DPMO, Sigma, Stability, absolute min/max, and rejection limits. These are computed from the combined mechanisation and production-type levels of all contributing microelements, using weighted averages up through the hierarchy.
For the full explanation of each metric, see Quality Metrics. For how rejection limits and distributions work, see Simulation.
Result Display
The canvas shows results in three places:
- Result block โ attached to each element, displays F/H/M/P rows. For operations and above, also shows setup, prep, P1 (per-piece), cycle time (when capacity โ 1), and sigma.
- Properties panel โ the right-side panel shows the full result details when an element is selected.
- Passport โ the "Time Structure" section renders the p1Breakdown as horizontal bar charts grouped by target, carrier, and stream. Each tag value gets a labelled bar with its percentage share.