Set the type of a step

The type of a step decides where its time goes: into the piece time, into setup or into preparation. Make one step a setup and another an auxiliary one.

On the canvas

The operation "Lathe work" with three steps. Under the operation is the card of its result. On the right the panels "Properties" and, under it, "Result" are open: the card shows the operation, the panel shows what is selected.

Steps

  1. Click the step "Set up the machine". In "Properties" the field "Type" says "Main", and the line under it "Group : Main".
  2. In the list "Type" choose "Setup". The badge S of the step changes colour, the row P of the card gets smaller and the row ST gets a time.
  3. Click the step "Load the blank".
  4. In the list "Type" choose "Auxiliary". The row P stays as it was; the two numbers after it change โ€” the shares of main and auxiliary steps.

Check

On the card: P โ€” 11.38 and 32|68, ST โ€” 6.16. Before the changes it was: P โ€” 17.54 and 100|0, ST โ€” 0.00.

If it did not work

The rule

There are nine types and three groups; the group is set by itself. "Main" and "Auxiliary" go into the piece time P. "Setup", "Technological Needs" and "Equipment Maintenance" go to ST. The other four types go to PR, the preparation.